Equity Two PLC Project


Project name :  1250A Main Electrical Infrastructure Installation Project

Customer NameEquity Two PLC

About the Customer :  Equity Two PLC, a Carson Cumberbatch property management company is renovating and refurbishing a property located at No 61, Janadhipathi Mawatha , Colombo 1 to add nearly 40,000 square feet of rentable office space to their existing capacity of 41,123 square feet.

Industry :  Commercial (Multistoried building)

Project Value :  Rs. 13 Million

Project Period & Year :  February – April, 2013 (Ongoing)

Scope of work undertaken:

Main electrical infrastructure installation including,

  • Design, Supply and Installation of Switchboards, Floor DBs, including 1250A ATS Panel,
  • Supply & Installation of 1200A Bus riser for six storied building.
  • Supply & Installation of cable tray systemsfor main cabling from Transformer and generator to ATS Panel.
  • Supply & installation of power cabling for machinery DBs, Lighting DBs and all factory machinery from respective DBs’.
  • Supply & Installation of automatic power factor correction capacitor bank.
  • Supply & installation of lighting protection system for the building.


Hioki appoints Rotax!

Rotax Limited has been appointed the exclusive sole agent of Hioki for the territory of Sri Lanka. Hioki a Japanese company founded in 1935, have been involved in the development, manufacture, and sale of electrical measuring instruments for several decades.

More...>>


Advanced MV Motor Control System for CPC

Our sister company Roche Projects Pvt. Ltd, recently installed & commissioned Sri Lanka's first medium voltage Soft Starter motor control system at our local petroleum corporation & refinery in Sapugaskanda.

More...>>


Opening of our "RLC"

On 12th of March, 2011 we were proud to open our 8,000 sq feet, double storied warehousing & stores complex based in Wattala.

More...>>


Distributors Wanted!!

Rotax Limited, recently increased their island wide presence by appointing 1 more distributor in Sri Lanka and by the end of the calendar year, we will appoint another 2 more distributors bringing our grand total to 6.


Jul-05 . Supply completed for Project in Ampare