QEG Lanka Project


Project name :  1250A Main Electrical Infrastructure Installation Project

Project name :  600kVA LT Industrial Electrical Installation Project

Customer Name :  QEG Lanka (Pvt) Limited

About the Customer :  QEG Lanka is a BOI approved manufacturing facility located in Pethiyagoda, Kelaniya which will be manufacturing a multi-purpose, versatile, non-combustible and unique construction with superior characteristics that enable better and faster indoor and outdoor construction.

Industry :  Construction Materials (Manufacturing)

Project Value :  Rs. 25 Million

Project Period & Year :  March – May, 2013 (Ongoing)

Scope of work undertaken:

Complete LT Electrical Installation including,

  • Design, Supply and Installation of Switchboards including 800A ATS Panel,
  • Supply & Installation of cable tray systems and steel conduiting for power, CCTV and data cabling.
  • Supply & installation of power cabling for machinery DBs, Lighting DBs and all factory machinery from respective DBs’.
  • Steel conduit point wiring and installation of LED high bay light fittings.
  • Supply & installation of lighting protection system for the premises.


Hioki appoints Rotax!

Rotax Limited has been appointed the exclusive sole agent of Hioki for the territory of Sri Lanka. Hioki a Japanese company founded in 1935, have been involved in the development, manufacture, and sale of electrical measuring instruments for several decades.

More...>>


Advanced MV Motor Control System for CPC

Our sister company Roche Projects Pvt. Ltd, recently installed & commissioned Sri Lanka's first medium voltage Soft Starter motor control system at our local petroleum corporation & refinery in Sapugaskanda.

More...>>


Opening of our "RLC"

On 12th of March, 2011 we were proud to open our 8,000 sq feet, double storied warehousing & stores complex based in Wattala.

More...>>


Distributors Wanted!!

Rotax Limited, recently increased their island wide presence by appointing 1 more distributor in Sri Lanka and by the end of the calendar year, we will appoint another 2 more distributors bringing our grand total to 6.


Jul-05 . Supply completed for Project in Ampare